Activity sequencing Involves reviewing activities and determining dependencies Mandatory dependencies: inherent in the nature of the work; hard logic Discretionary dependencies: defined by the project team; soft logic External dependencies: involve relationships between project and non-project activities Examples of each type of dependency from your team projects? You must determine dependencies in order to use critical path analysis 2021/2/21 112021/2/21 11 Activity Sequencing ◼ Involves reviewing activities and determining dependencies ◼ Mandatory dependencies: inherent in the nature of the work; hard logic ◼ Discretionary dependencies: defined by the project team; soft logic ◼ External dependencies: involve relationships between project and non-project activities ◼ Examples of each type of dependency from your team projects? ◼ You must determine dependencies in order to use critical path analysis