The Three month review a Three units scheduled for completion Two units actually completed $300,000 budgeted at this point $300,000 actually spent Optimist pm: A little behind schedule but right on the cost plan10 The Three Month Review Three units scheduled for completion Three units scheduled for completion Two units actually completed Two units actually completed $300,000 budgeted at this point $300,000 budgeted at this point $300,000 actually spent $300,000 actually spent Optimist PM: “A little behind schedule but Optimist PM: “A little behind schedule but right on the cost plan.” right on the cost plan