Earned Value Concept Earned value Concept的由来 ◆ Earned value Concept的分析 ◆ Earned value Concept的应用
Earned Value Concept Earned Value Concept 的由来 Earned Value Concept 的分析 Earned Value Concept 的应用
上 Earned Value Concept Ei ◆问题: A project authorized amount is $100,000 over 12-month period. After six months of performance, the project spent $29,000 of its planned $32, 000 in budget. What can one discern from exam ining the performance at the half way of the project?
问题: A project authorized amount is $100,000 over 12-month period. After six months of performance, the project spent $29,000 of its planned $32,000 in budget. What can one discern from examining the performance at the half way of the project? Earned Value Concept 由来
100 60 Planned Cost 40 Actual cost T Traditional Two-Dimensional Cost Management
T 0 40 60 100 $ 80 20 Traditional Two-Dimensional Cost Management Actual Cost Planned Cost
100 80 Planned-Cost 40 Actual cost 20 Earned value T Three-Dimensional earned value performance Measurement
T 0 40 60 100 $ 80 20 Three-Dimensional Earned Value Performance Measurement Actual Cost Earned Value Planned Cost
Earned Value Concept由来(1) 作业一月三月三月「四月「五月六月预算 数据 150 150 实际=120 150 实际值=150 计划1 150 200 实际但=150 计划=0 实际位 总计 计划值=459x0小于预算值 实际值=420 600
Earned Value Concept由来(1)
Earned value Concept由来(2) 作业一月二月「三月「四月五月「六月预算 150 150 羸得值=150 实际值=120 计划位=150 得 50 实际住=150 划=1501 200 麻得位=50 实际值=150 计划值=0 100 羸得 实际 0 总计 计划值=450530进度带后 实际值=42050费用超支 600
Earned Value Concept 由来(2)
Earned Value Concept由来(3) ◆EVC出现在美国工业工厂计算COST VARIANCE ◆1962-1965:PERT1958年在美海军中出 现,1962,PERT/Cost出现 ◆1967—现在:美国DOD,C/SCSC: Cost/Schedule Control Systems Criteria 在1967.12出现
EVC出现在美国工业工厂计算COST VARIANCE. 1962-1965: PERT1958年在美海军中出 现. 1962, PERT/Cost 出现. 1967—现在: 美国DOD, C/SCSC: Cost/Schedule Control Systems Criteria 在1967.12出现. Earned Value Concept 由来(3)